Between September 19th and Sept 30th Reliablehosting will be relocating dedicated servers to a new UPS power system. To make this change, each dedicated server will be temporarily powered down, moved into new seismic equipment racks, and connected to the new UPS power distribution system and powered back on. It is expected to take approximately 40 minutes to complete this work for each server. We have had some servers take longer due to mounting changed needed for the new equipment racks. Below is a revised schedule noting what work has been completed, and what remains. Our sincere apologies for the disruption this work may cause you, but we do consider this work vital to the long term stability of our network and service offerings.
Server work schedule, work will be performed between 9:00am and 8:00pm pacific time
Mon Sept 19: ds77 - ds149, co112 - co118 (completed)
Mon Sept 19: any remaining servers using 216.131.94.1-126 (completed)
Tue Sept 20: ds210 - ds234, ph1 - ph4 (completed)
Tue Sept 20: ds1 - ds76, wn1 - wn5 (completed)
Wed Sept 21: co1 - co6, co57 - co109 (completed)
Thu Sept 22: any remaining servers using 216.131.95.1-254 (completed)
Thu Sept 22: pa & colo (completed)
Fri Sept 23: co7 - co55 (revised schedule)
Fri Sept 23: co119 - co215 (revised schedule)
Fri Sept 23: wn24 - wn48, wn51+
Mon Sept 23: ds150 - ds209 (revised schedule)
Mon Sept 26: any remaining servers using 216.131.96.1-254 (revised schedule)
Mon Sept 26: servers using load balancer switches
Tue Sept 27: gt1 - gt98
Wed Sept 28: virtual and vps servers
Wed Sept 28: any remaining servers using 216.131.127.1-126 (revised schedule)
Thu Sept 29: as needed
Fri Sept 30: as needed