• IP addresses are NOT logged in this forum so there's no point asking. Please note that this forum is full of homophobes, racists, lunatics, schizophrenics & absolute nut jobs with a smattering of geniuses, Chinese chauvinists, Moderate Muslims and last but not least a couple of "know-it-alls" constantly sprouting their dubious wisdom. If you believe that content generated by unsavory characters might cause you offense PLEASE LEAVE NOW! Sammyboy Admin and Staff are not responsible for your hurt feelings should you choose to read any of the content here.

    The OTHER forum is HERE so please stop asking.

Leong Sze Hian: Bad budgetting or construction costs led to 70% increase by LTA?

Confuseous

Alfrescian (Inf)
Asset
Joined
Dec 30, 2010
Messages
12,730
Points
113
1 more MRT station?

The number of MRT stations will increase by one more, from 33 to 34. So, a three per cent increase in the number of stations has contributed to a 73 per cent increase in the costs.

2 more km of tracks?

The length of MRT tracks will increase by two km from 40 to 42 km. So, a five per cent increase in the length of MRT tracks has also contributed to a 73 per cent in the costs.

Get more firms to bid?

As to “(LTA), which also said it is taking steps – like inviting more firms to bid for projects – to rein in prices”, does this imply that they did not do enough in the past, to invite more firms to bid for projects – to rein in prices?

Detailed breakdown?

We need a more detailed breakdown and accounting as to “Half of this $8.7 billion increase was attributed to a sharp rise in construction cost, with the other half linked to a number of changes to the project”.

- http://leongszehian.com/?p=1987
 